MOD-012-0: Dynamics Data for Transmission System Modeling and Simulation
Purpose
To establish consistent data requirements, reporting procedures, and system models to be used in the analysis of the reliability of the interconnected transmission systems.
Applicability
- Transmission Owners specified in the data requirements and reporting procedures of MOD-013-0_R1
- Transmission Planners specified in the data requirements and reporting procedures of MOD-013-0_R1
- Generator Owners specified in the data requirements and reporting procedures of MOD-013-0_R1
- Resource Planners specified in the data requirements and reporting procedures of MOD-013-0_R1
Effective Date
April 1, 2005
Requirements
R1. The Transmission Owners, Transmission Planners, Generator Owners, and Resource Planners (specified in the data requirements and reporting procedures of MOD-013-0_R1) shall provide appropriate equipment characteristics and system data in compliance with the respective Interconnection-wide Regional dynamics system modeling and simulation data requirements and reporting procedures as defined in Reliability Standard MOD-013-0_R1.
R2. The Transmission Owners, Transmission Planners, Generator Owners, and Resource Planners (specified in the data requirements and reporting procedures of MOD-013-0_R1) shall provide dynamics system modeling and simulation datato its Regional Reliability Organization(s), NERC, and those entities specified within the applicable reporting procedures identified in Reliability Standard MOD-013-0_R1. If no schedule exists, then these entities shall provide data on request (30 calendar days).
Measures
M1. The Transmission Owners, Transmission Planners, Generator Owners, and Resource Planners (specified in the data requirements and reporting procedures of MOD-013-0_R1) shall each have evidence that it provided equipment characteristics and system data for dynamics system modeling and simulation in accordance withReliability Standard MOD-012-0_R1 and Reliability Standard MOD-012-0_R2.