Purpose:
To prevent and detect unauthorized changes to BES Cyber Systems by specifying configuration change management and vulnerability assessment requirements in support of protecting BES Cyber Systems from compromise that could lead to misoperation or instability in the Bulk Electric System (BES).
Applicability:
4.1.
…
Read more ›
Purpose
To provide System Operators with the capabilities necessary to monitor and analyze data needed to perform their reliability functions.
Applicability
Effective Date:
See Implementation Plan
Requirements and Measures
R1.
…
Read more ›
Purpose: To prevent instability, uncontrolled separation, or Cascading outages that adversely impact the reliability of the Interconnection by ensuring prompt action to prevent or mitigate such occurrences.
Applicability:
4.1.
…
Read more ›
Purpose
To ensure that load-responsive protective relays are expected to not trip in response to stable power swings during non-Fault conditions.
Applicability
4.1. Functional Entities:
4.1.1 Generator Owner that applies load-responsive protective relays as described in PRC-026-1 – Attachment A at the terminals of the Elements listed in Section 4.2,
…
Read more ›
Purpose
To establish design and documentation requirements for automatic underfrequency load shedding (UFLS) programs to arrest declining frequency, assist recovery of frequency following underfrequency events and provide last resort system preservation measures.
Applicability
4.1. Planning Coordinators
4.2.
…
Read more ›
Purpose
To ensure the Western Interconnection is operated in a coordinated manner under normal and abnormal conditions by establishing the performance criteria for WECC power system stabilizers.
Applicability
4.1. Generator Operator
4.2. Generator Owner
Facilities
This standard applies to synchronous generators,
…
Read more ›
Purpose
To establish consistent validation requirements to facilitate the collection of accurate data and building of planning models to analyze the reliability of the interconnected transmission system.
Applicability
4.1. Functional Entities:
4.1.1 Planning Authority and Planning Coordinator (hereafter referred to as “Planning Coordinator”)
“Planning Coordinator”) This proposed standard combines “Planning Authority” with “Planning Coordinator” in the list of applicable functional entities.
…
Read more ›
Purpose
To manage electronic access to BES Cyber Systems by specifying a controlled Electronic Security Perimeter in support of protecting BES Cyber Systems against compromise that could lead to misoperation or instability in the BES.
Applicability
4.1. Functional Entities: For the purpose of the requirements contained herein,
…
Read more ›
Purpose
To establish Interpersonal Communication capabilities necessary to maintain reliability.
Applicability
4.1. Transmission Operator
4.2. Balancing Authority
4.3. Reliability Coordinator
4.4. Distribution Provider
4.5. Generator Operator
Effective Date
The first day of the second calendar quarter beyond the date that this standard is approved by applicable regulatory authorities,
…
Read more ›
Purpose
To specify the quantity and types of Contingency Reserve required to ensure reliability under normal and abnormal conditions.
Applicability
4.1 Balancing Authority
4.1.1. The Balancing Authority is the responsible entity unless the Balancing Authority is a member of a Reserve Sharing Group,
…
Read more ›