Resource and Demand Balancing

BAL-002-3: Disturbance Control Standard – Contingency Reserve for Recovery from a Balancing Contingency Even

Purpose
To ensure the Balancing Authority or Reserve Sharing Group balances resources and demand and returns the Balancing Authority’s or Reserve Sharing Group’s Area Control Error to defined values (subject to applicable limits) following a Reportable Balancing Contingency Event.

Applicability

  • Balancing Authorities
  • A Balancing Authority that is a member of a Reserve Sharing Group is the Responsible Entity only in periods during which the Balancing Authority is not in active status under the applicable agreement or governing rules for the Reserve Sharing Group
  • Reserve Sharing Group

Effective Date: 4/1/2019

Requirements
R1

Read more ›



BAL-005-1: Balancing Authority Control

Purpose
This standard establishes requirements for acquiring data necessary to calculate Reporting Area Control Error (Reporting ACE).  The standard also specifies a minimum periodicity, accuracy, and availability requirement for acquisition of the data and for providing the information to the System Operator.

Applicability

  • Balancing Authorities

Effective Date 
1/1/2019

Requirements

R1.    

Read more ›



BAL-004-WECC-3: Automatic Time Error Correction

Purpose

To maintain Interconnection frequency and to ensure that Time Error Corrections and Primary Inadvertent Interchange (PII) payback are effectively conducted in a manner that does not adversely affect the reliability of the Interconnection.

Applicability
Functional Entities: Balancing Authorities that operate synchronously in the Western Interconnection.

Read more ›



BAL-502-RF-03: Planning Resource Adequacy Analysis, Assessment and Documentation

Purpose
To establish common criteria, based on “one day in ten year” loss of Load expectation principles, for the analysis, assessment and documentation of Resource Adequacy for Load in the ReliabilityFirst Corporation (RFC) region

Applicability
Planning Coordinator

Effective Date
1/1/2018

Requirements

R1 The Planning Coordinator shall perform and document a Resource Adequacy analysis annually.

Read more ›



BAL-002-WECC-2a

Purpose

To specify the quantity and types of Contingency Reserve required to ensure reliability under normal and abnormal conditions.

Applicability

4.1 Balancing Authority

4.1.1.  The Balancing Authority is the responsible entity unless the Balancing Authority is a member of a Reserve Sharing Group,

Read more ›



BAL-003-1.1 – Frequency Response and Frequency Bias Setting

Purpose

To require sufficient Frequency Response from the Balancing Authority (BA)  to maintain Interconnection Frequency within predefined bounds by arresting frequency deviations and supporting frequency until the frequency is restored to its scheduled value.  To provide consistent methods for measuring Frequency Response and determining the Frequency Bias Setting.

Read more ›



BAL-001-2 – Real Power Balancing Control Performance

Purpose
To control Interconnection frequency within defined limits.

Applicability
4.1. Balancing Authority

4.1.1 A Balancing Authority receiving Overlap Regulation Service is not subject to Control Performance Standard 1 (CPS1) or Balancing Authority ACE Limit (BAAL) compliance evaluation

4.1.2 A Balancing Authority that is a member of a Regulation Reserve Sharing Group is the Responsible Entity only in periods during which the Balancing Authority is not in active status under the applicable agreement or the governing rules for the Regulation Reserve Sharing Group

4.2.

Read more ›



BAL-001-TRE-1: Primary Frequency Response in the ERCOT Region

Purpose
To maintain Interconnection steady-state frequency within defined limits.

Applicability

  • Balancing Authority
  • Generator Owners
  • Generator Operators

Exemptions
4.2.1 Existing generating facilities regulated by the U.S. Nuclear Regulatory Commission prior to the Effective Date are exempt from Standard BAL- 001-TRE-01.